The City of Calgary Land Use Bylaw 1P2007
Top of page
Permitted Uses That Meet All Requirements
28
1
Where a development permit application is for a permitted use in a building or on a parcel and the proposed development conforms to all of the applicable requirements and rules of this Bylaw, the Development Authority must approve the application and issue the development permit.
2
The Development Authority may, as a condition of issuing a development permit for a permitted use, require the applicant to construct or pay for the construction of the following that are necessary to serve the development:
3
The Development Authority may, as a condition of issuing a development permit for a permitted use, impose conditions in respect of the following matters:
4
The Development Authority may, as a condition of issuing a development permit for a permitted use, require the applicant to enter into an agreement with the City to do any or all of the following:
a
to construct or pay for the construction of a public thoroughfare required to give access to the development;
ii
pedestrian walkways to connect the pedestrian walkway system serving the development with a pedestrian walkway system that serves or is proposed to serve an adjacent development; or
c
to install or pay for installation of public utilities, other than telecommunications systems or works, that are necessary to serve the development;
5
Where a development is located in the floodway, flood fringe or overland flow area, the Development Authority may, as a condition of issuing the development permit, require building or site design measures to mitigate the potential impact or obstruction of floodwaters.
6
Where a development permit application for a permitted use does not show that the development conforms to all of the applicable requirements and rules of this Bylaw, the Development Authority may, as a condition of issuing the development permit, require that the applicant amend specific elements of the plans to conform with the applicable requirements.
6.1
The Development Authority may, as a condition of issuing a development permit for a permitted use on a parcel adjacent to a freight rail corridor:
b
require the mitigations identified in subsection (a) to be incorporated into the development for the life of the development.
7
The Development Authority may require the fulfillment of the conditions referred to in this section before releasing the development permit.