The target timeline for a detailed multi-disciplinary response to a development permit application is either 35 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a multi-disciplinary development permit application is either 120 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a Land Use Amendment application is either 49 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a Land Use Amendment is either 180 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a development permit application is either 35 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a development permit application is either 35 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a multi-disciplinary development permit application is either 120 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a multi-disciplinary development permit application is either 120 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a Land Use Amendment application is either 49 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a Land Use Amendment application is either 49 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a Land Use Amendment is either 180 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a Land Use Amendment is either 180 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a Subdivision by Tentative Plan is 28 days from the date the application is deemed complete by administration.
The target timeline for a decision on a Subdivision by Tentative Plan application is 60 days from the date the application is deemed complete by administration.
The target timeline for a decision on a residential infill development permit application is 90 days from receipt of application.
The target timeline for a detailed multi-disciplinary response to a Subdivision by Tentative Plan is 28 days from the date the application is deemed complete by administration.
The target timeline for a detailed multi-disciplinary response to a Subdivision by Tentative Plan is 28 days from the date the application is deemed complete by administration.
The target timeline for a decision on a Subdivision by Tentative Plan application is 60 days from the date the application is deemed complete by administration.
The target timeline for a decision on a Subdivision by Tentative Plan application is 60 days from the date the application is deemed complete by administration.