Demolish a building

Includes low-density residential, multi-residential, and commercial projects that require building demolition or removal.

Before you apply

Use this page to help guide you through submitting a complete application. We will explain when you need a permit, what permits you need, what your application requirements are and go over some common rules relating to your project.

Do you need a permit?

A demolition permit is required if:

  • you are demolishing a building from a site
  • moving a building from a site
  • partial building demolition
  • reducing a building to its foundation and rebuilding.

In most cases, a demolition permit is not required for:

How much will it cost?

Building safety approval - Building permit Fee schedule Permit fee
Demolish or move a building

building permit fee schedule

Varies

Please use the Building permit fee calculator - Demolition​ to estimate your fee.

How do you pay for a permit?

Online submissions

For online submissions you will pay your permit fees in full at the time of your application using a credit card

In person submissions

You will be required to pay in full at the time of your application. You may pay by credit or debit card, cheque or cash.

How long will it take to get a permit?

Timelines indicated are not a guarantee and depend on volumes, application completeness, and the applicant’s timely replies to additional information requests from the City.

Tip: To avoid delays in processing your application, make sure your application includes all the required documents, plans and information listed on the checklist below. 

 

See the tips for a smooth application for details on submitting a complete application.

Building safety approval - Building permit Our process Timeline
Application is reviewed to ensure it matches the approved development permit and reviewed for safety code compliance 7 days

When does your permit expire?

Permit type Expiry (from date of issuance)
Demolition permit 180 days

You will receive a permit expiry reminder in the mail. If you need more time, you can extend your permit. Visit the extend or reinstate your permit page.

Information to consider when demolishing or removing a building

collapsed all

How to prepare your application

1. Prepare the application details

You will need to know:

  • The project address
  • Who is applying (the homeowner or someone representing the owner)
  • Who will be doing the work (licenced demolition contractor)
  • What you are applying for
  • Project details, including the size of the deck

2. Prepare the required documents and plans

Specific drawing and supporting document requirements are listed on the permit checklist. You must provide all the required drawings and documents when you submit your application.

Demolition Permit application requirements

Supporting Documents

Supporting Documents

1. Utility Disconnection

Review the checklist and determine which utilities require disconnection. Follow the utility disconnection instructions and obtain the required signatures for water, electrical and gas services on your service disconnection request form before applying. The time it takes to receive each signature depends on each utility provider.

For more information regarding the various utilities’ procedures and applicable fees, please contact that particular utility office.

Doing work to a building that requires shut-offs with no demolition planned requires calling each individual utility provider to ask for their services to be disconnected. If only the services will be shut off, no demolition permit is required.

See all water service disconnection changes effective July 2021.

2. Asbestos form

 Asbestos abatement form – This form only needs to be completed for houses built prior to 1990.

Public tree disclosure statement

  • Indicate yes or no if there is a public tree on the City lands within six meters of and/or overhanging your property
  • If there are public trees, show these trees on your site plan and complete the rest of the form.
  • If you are not sure if there are public trees, you can use the city’s tree map (may not be up to date for your property) or contact 3-1-1 for a development tree inquiry.
3. Advanced weather forecasting system
  1. Only required if the building is five storeys or greater in height
  2. Refer to the advanced weather forecasting system – building regulations advisory
4. Public protection site safety plan
  1. Only required if the building is 5 storeys or greater in height
  2. Refer to the public site safety plan – building regulations advisory

Plans

Apply

Tips for a smooth application process

Before you apply

Download the checklist and check each application requirement as you prepare to submit your application. Items listed on the checklist are the minimum requirements. We might need more information after we review your application.

Provide all required documents on the checklist, including drawings, supporting material, and any additional forms. If you are not sure if something is required, contact the Planning Services Centre

Use sample drawings to review what you need to include on your plans

Double check your documents are completed and make sure you have all required items on your plans before you upload them

After you apply

The Planning Services Centre may contact you for more information required for your application. Follow-up on requests for more information as quickly as possible. 

Use the Job Access Code (JAC) to check status updates for your application on calgary.ca/vista

  • You’ll get a JAC by e-mail after you’ve submitted your application. If you did not receive a JAC number, contact the Planning Services Centre.
  • Checking your application’s status using your JAC will provide you with timely updates about the status of your application

What is a complete application?

A complete application means that you have provided all the necessary requirements for our teams to complete their reviews. You should provide everything listed on the Complete Application Requirement List and the Guide to a Complete Application (if applicable), including plans, supporting documents and payment.

An application for a permit may be refused  if, within ninety (90) days from the date of receipt,  if adequate information and documentation is not supplied as requested by the Safety Codes Officer. Should a permit be considered for refusal, the applicant will be given notification in writing and 30 days to resubmit the missing information. For more information, please review Building advisory A19-002 building permit complete application.

Apply online

To apply online, you need a myID account. Create a myID account..

Apply in-person

Complete the application form.

Once you have gathered all required documents, you can apply for your permit in person by visiting the Planning Services Centre.

After you apply

How to check the status of your permit

After you submit your application online, you will get a confirmation email with a Job Access Code (JAC).

To track your application and check its status, enter your Job Access Code in Vista.

If you need help or have questions, contact our Planning Services Centre

What Inspections do you need?

Demolition permit Inspection

Please note that the inspection process is dynamic, and an inspection outcome depends on the construction method and site conditions at time of inspection. Please contact the Technical Assistance Centre for more information.

How do you book your inspections?

Visit building inspections for information on how to book, cancel or reschedule an inspection, permit expiry and the requirements for each inspection type.

Contractors

If you have a vista account:

If you do not have a Vista acount:

Planning Services Centre

Hours:
Monday - Friday
8 a.m. - 4 p.m. (MT)

Live chat:
calgary.ca/livechat

Call:
403-268-5311

In person: 
Planning Services Centre,
3rd floor, Municipal building 
800 Macleod Trail SE

Book an eAppointment for in person services at appointment.calgary.ca


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null