Soccer Centre Dome & Artificial Turf Field Upgrade
Soccer Centre Dome now open for bookings
As of May 31, 2025, the air-supported dome and artificial turf field is open for public bookings, complementing the existing amenities at the MaxWell Soccer Centre. The facility is set to inflate new opportunities for competitive and recreational users, providing players with a high-quality, year-round space for practice and play.
We put the finishing touches on the facility through the summer and are please to announce that the construction phase of this project will be fully complete by November 2025.
Design
The MaxWell Soccer Centre Dome and Artificial Turf Field Upgrade included:
- Upgrading the natural turf field to a competition-sized 11 vs. 11 indoor artificial turf field.
- Building an air-supported structure (dome) over the new artificial turf field.
- A new amenity building including participant change rooms, a referee change room and a universal public washroom.
- Improving the parking lot infrastructure by paving the west parking lot and adding approximately 100 additional parking spots.
- Upgrading the storm water management to prevent localized flooding.
Benefit
This project:
- Created a full-sized indoor rectangular field, providing citizens with a high-quality, year-round practice and play space.
- Complemented existing amenities, accommodating a broad range of sport and recreation opportunities.
- Increased the capacity to host tournaments.
Investment in this project also generated approximately 150 jobs and contributed $21.2 million to the GDP1.
Timeline
- 2019 – Council approves Administration’s proposed One Calgary four-year capital budget, including funding for maintenance and renewals at existing City recreation facilities.
- 2021 – Council approves the Revised Calgary Recreation Capital Investment Strategy, Report C2021-0911 (to provide funding for the air-inflated dome over the new artificial turf field)
- August 2021 – Design development begins
- April 2024 – Construction begins
- Fall 2024 – N.W. parking lot improvements complete
- May 2025 – Facility reopens to the public
- December 2025 – Construction complete
Budget
The upgrades represent a $28 million investment; $3.6M of this funding was provided by the Government of Alberta’s Municipal Sustainability Initiative, with the remaining funds provided through the Revised Calgary Recreation Capital Investment Strategy and Calgary 2023-2026 Service Plans and Budgets. Some funding was also provided from the Centralized Climate Fund.
1Based on estimates from Infrastructure Calgary’s economic impact assessment model