East Belvedere Feeder Main
Project status - March 2026
We are making progress on construction to install the feeder main which will take place on the north side of Memorial Drive (westbound lanes) between Abbeydale Drive SE and the intersection at 68 Street S.E.
This will result in closure of the westbound lanes. Traffic will be detoured to the south lanes, so two-way, east-west, traffic can be maintained.
Once this work is complete in May (approximate) the westbound lanes of Memorial Drive will be paved and reopened and crews will then work at the intersection at 68th Street and Memorial Drive, which will be impacted with some traffic delays until the end of June (approximate). Signage will be in place to direct drivers. Please see the maps below.
Meanwhile, we are continuing with work to install the feeder main east of Memorial Drive N.E.
Please note, a section of parking is prohibited on Applegrove Cresent daily from 8 a.m. – 4 p.m. for the duration of the project which is expected to be complete by August 2026.
A section of the area pathway will also be closed from approximately February to Fall 2026. Please see the map below for additional information.
Project background
The City of Calgary is building a new 2-kilometre-long feeder main which is an essential piece of water infrastructure that will bring clean and reliable drinking water to current and future development within the East Belvedere community.
The feeder main is being constructed in phases.
- Phase 1 includes the installation of a feeder main along Memorial Drive from 68 Street S.E. to 84 Street S.E. and then eastward along a future extension of Memorial Drive.
- Phase 2a, where construction also starts this fall, includes the portion from 84 Street S.E. to 100 Street S.E. along the future extension of Memorial Drive.
- Phase 2b, which was completed this spring (2025) includes the portion on 100 Street S.E. on the future extension of Memorial Drive travelling south to 17 Avenue S.E.
Construction for Phase 1 is expected to begin winter 2025. Phase 2a began fall 2025. The first section of construction for Phase 1 takes place in the grassed area east of 68th Street S.E.. The entire feeder main is expected to be complete by fall of 2026.
Project timeline
Construction
- Phase 1 – February 2026 to August 2026
- Phase 2A – September 2025 to spring/summer 2026
- Phase 2B – Complete
Related projects
Memorial Drive Extension Project
The City of Calgary is extending Memorial Drive east from Abbeydale and Applewood Park, over Stoney Trail and connecting to 84 Street E.
Project maps
Construction area and impacts
This map shows the stage of work on the westbound lanes of Memorial Drive and the work area at the intersection of 68 Street S.E.
This map shows the pathway detour, laydown area for equipment and supply storage and the parking ban.
This map shows all stages of the Belvedere Feeder Main project
Construction impacts
- A section of parking is prohibited on Applegrove Crescent daily from 8 a.m. – 4 p.m. for the duration of the project which is expected to be complete by August 2026.
- Residents will notice an increase in noise.
- The contractor will take steps to limit the amount of dust in the work area.
- There will be construction truck traffic in the area.
- Construction hours are 7 a.m. to 10 p.m. on weekdays and 9 a.m. to 10 p.m. on weekends and holidays. Please note: these times and hours may extend in order to meet the project completion schedule.
- The City does not expect vibration impacts from construction to affect private properties.
- A section of the area pathway will be closed from approximately February 2026 to Fall 2026.
- Access to area businesses may be limited but will always be maintained.
Frequently asked questions
Why is this feeder main needed?
With Calgary’s population growing, this feeder main is needed to support current and future growth in the East Belvedere area.
When will construction start?
Our contractor is finalizing plans and we expect to begin mobilizing to the site in early/mid December 2025.
What area will construction begin in?
We are starting just east of 68th Street S.E. in the grassed area south of Abalone Way. Residents who back onto that area will be notified via construction notices that will be delivered to their homes prior to construction. These will detail the specific impacts and timelines.
What is happening to the cement barriers that have artwork that were at the end of Memorial Drive?
We will be moving these permanently and they will not be required in the future as Memorial Drive is being extended as part of Memorial Drive Extension project.
Will any trees be removed as part of the project?
We did have to remove some trees in the greenspace area east of Memorial Drive and we are making our best effort to replant the trees in consultation with the Community Association. So far we have relocated 15 trees and will replant trees we are unable to relocate to sustain our City’s tree canopy.
Will the intersection of Memorial Drive and 68th Street be closed?
There may be lane closures but we plan to keep traffic flowing in all directions. We will have more information on this as we get closer to construction in this area which we estimate will be in Q1 of 2026.