We are upgrading infrastructure along 14 and 15 Avenue S. to provide dedicated spaces for walking and wheeling (biking, scootering, and skateboarding). These changes will support community health and wellness, and enhance safety, accessibility, and overall mobility for Calgarians and visitors.

Parking

Project update: May 2025

14 Ave S - Pedestrian infrastructure upgrades and concrete work along 14 Avenue S. is underway. Construction is being conducted in short sections, moving eastward from 14 Street toward Macleod Trail. Each section comprises three phases of work: enabling work and streetlight upgrades, pedestrian infrastructure enhancements, and concrete work and road rehabilitation.

15 Ave S - Construction along 15 Avenue S. began in mid-May. On the east end of the corridor, starting at Macleod Trail, pedestrian infrastructure upgrades and concrete work are underway. On the west end, crews are focusing on completing the water main replacement between 6 Street S.W. and 8 Street S.W.

Parking - See a map of alternative parking options.

Thank you for your cooperation and patience as we work to improve infrastructure in the area. Your safety remains our top priority.

Construction schedule: Fall 2024 to Summer 2026

Please note that the construction schedule is subject to change due to various factors such as weather, supply chain issues and site access.

14 Avenue S.

Phase 1 – Fall 2024 to Fall 2025 (in progress): Enabling work and streetlight upgrades

Construction details:

Construction will occur intermittently throughout the remainder of 2025.

Work includes:

  • Updated traffic signals
  • Streetlight work to rebalance lighting levels

Phase 2 – April to June 2025 (in progress): Pedestrian infrastructure upgrades and concrete work

Construction details:

Upgrades will improve pedestrian accessibility along 14 Avenue S. 

Work includes:

  • Concrete repairs to curbs and sidewalks
  • Raised crosswalk at 14 Avenue and 6 Street S.W.
  • Installation of new wheelchair ramps

Scope of work:

Construction is being conducted in short sections, starting at 14 Street and moving eastward toward Macleod Trail.

Phase 3– May to August 2025 (in progress): Repaving

Construction details:

Repaving along 14 Avenue S. will improve the road and remove the current painted wheeling lane.  This lane will be replaced with a new protected bike lane on 15 Avenue S.

Work includes:

  • Removing the top layer of old asphalt (milling) and paving

Scope of work:

Construction will be carried out in three sections, starting at Macleod Trail and progressing westward toward 14 Street. To minimize the duration of the project, milling and paving work will commence at 6 a.m. each day.

Please be aware that there will be temporary disruptions to driveway access. For properties undergoing repaving, we recommend parking your vehicle in an alternative location before construction begins to avoid being blocked in.

  • Section 1 – Repaving along 14 Avenue from 14 Street to 7 Street S.W. is anticipated to start the end of May.
    • Phase 1: Rolling closures from 14 Street to 7 Street S.W. for milling (removing old asphalt) are expected to last 1-2 days. As work progresses, traffic control will reopen sections of the road. Please follow the instructions of traffic control personnel.
    • Phase 2: Full road closure from 14 Street to 9 Street S.W. as crews apply new asphalt is expected to last 1-2 days. Local access may be permitted depending on the progress of the work.
    • Phase 3: Full road closure from 9 Street to 7 Street S.W. as crews apply new asphalt is expected to last 1-2 days. Local access may be permitted depending on the progress of the work.
  • Section 2 – Repaving along 14 Avenue from 7 Street to 4 Street S.W. is anticipated to start mid-June.
  • Section 3 - Repaving along 14 Avenue from 4 Street to 1 Street S.E. is anticipated to start mid-June.

After construction is complete, 14 Avenue will be converted back to a two-way road to improve traffic circulation and provide more efficient routes for drivers.

15 Avenue S.

Phase 1 – Fall 2024 to Fall 2025 (in progress): Enabling work and streetlight upgrades

Construction details:

Construction will occur intermittently throughout the remainder of 2025.

Work includes:

  • New traffic signals on 15 Avenue at Macleod Trail and 2 Street S.W. will support the new wheeling lanes
  • Streetlight work to rebalance lighting levels

Phase 2 – Mid-May to Sept. 2025 (in progress): Pedestrian infrastructure upgrades and concrete work

Construction details:

Upgrades will improve pedestrian accessibility along 15 Avenue S. 

Work includes:

  • Roadwork
  • Concrete repairs to curbs and sidewalks
  • Installation of new wheelchair ramps
  • Relocation and replacement of stormwater drains

Scope of work:

Construction will start at Macleod Trail and move westward toward 14 Street, approximately one or two blocks at a time. During construction, there may be temporary lane closures and detours. Pedestrians can expect to be detoured when sidewalks are being reconstructed.

Driveway Access: We strive to maintain driveway access. Where feasible, driveway accesses will be reconstructed one half at a time, allowing vehicles to enter and exit throughout the construction period. Flag persons will be present to provide direction as needed. If full driveway access closure is required, advance notice will be provided.

 

Phase 3 – Mid-May to June 2025 (in progress): Water main replacement

Construction details:

The water main on 15 Avenue S. from 6 Street S.W. to 8 Street S.W. is proactively being replaced.

Work includes:

  • Preparation work, including hydrovacing, saw cutting and temporary water material setup in advance.
  • Excavation and trenching
  • Pipe installation
  • Backfill and surface restoration. Note - initial surface restoration will be done with asphalt and gravel to quickly restore access to affected properties. Later in the project, permanent curbs, sidewalks, and driveway aprons will be installed with concrete.

Scope of work: 

15th Avenue S. watermain phasing plan

Construction will begin the week of May 19, 2025, and will take approximately 6 weeks to complete. Work will be completed in short sections, starting on the south side of the block between 7 and 8 Street S.W.

The following dates are subject to change or shift based on weather, ground conditions, and construction progress:

  • Phase 1: May 20 to June 9 - Water main replacement on 15 Avenue S.W. will begin on the east side of 8 Street S.W., between 8 Street and 7 Street.
    • Access: During construction, there will be temporary road closures and detours. Residents and businesses can expect temporary disruptions to driveway access. Local access will be allowed whenever possible. Please follow all posted signs and instructions from traffic control flaggers.
  • Phase 2: May 29 to June 2 - Water tie-in on the west side of the intersection of 8 Street and 15 Avenue S.W. will occur over the May 23 weekend. To minimize disruption, work will start at 5 a.m. and happen up to 24 hours per day over the weekend.
    • Access: Two-way traffic on 8 Street will be maintained with some lane reductions. Please watch for posted detour signage.
  • Phase 3: May 28 – May 29 - Complete watermain replacement on the east side of the intersection of 8 Street and 15 Avenue S.W. will occur over the May 30 weekend. To minimize disruption, work will happen up to 24 hours per day over the weekend.
    • Access: Two-way traffic on 8 Street will be maintained with some lane reductions. Please watch for posted detour signage.
  • Phase 4: June 2 – June 5 - Water main replacement in the intersection of 15 Avenue and 7 Street S.W.
    • Access: Two-way traffic on 7 Street will be maintained with some lane reductions. Please watch for posted detour signage.
  • Phase 5: June 5 – June 13 – Water main tie-ins and replacement in the intersection of 15 Avenue & 6 Street S.W.
    • Access: Two-way traffic on 7 Street will be maintained with some lane reductions. Please watch for posted detour signage.
  • Phase 6: June 5 – June 13 - Complete the watermain replacement on 15 Avenue S.W. between 6 Street and 7 Street.
    • Access: During construction, there will be temporary road closures and detours. Residents and businesses may experience disruptions when accessing driveways. Local access will be allowed whenever possible. Please follow all posted signs and instructions from traffic control flaggers.

Phase 4 – Fall 2025 to Summer 2026 (not started): Repaving

Construction details:

The final phase of construction involves repaving 15 Avenue

Work includes:

  • Removing the old asphalt (milling) and paving,
  • Concrete work for the protected two-way wheeling lane from 11 Street S.W. to Macleod Trail.

Temporary Construction Impacts

Traffic

Unless otherwise noted, the road will remain open, but there may be minor delays or changes in traffic patterns due to construction activities.

Sidewalks

During sidewalk repairs and replacement, pedestrians will be detoured to alternate streets or on temporary wooden ramps through the impacted area. Flag-persons will be present to assist with pedestrian activity.

On-street cycling

For your safety, please avoid traveling through construction zones. Cyclists should use alternate routes to bypass areas where construction is taking place.

Driveway access

We are committed to minimizing disruptions to driveway access. Where feasible, driveway accesses will be reconstructed one half at a time, allowing vehicles to enter and exit throughout the construction period. Flag persons will also be present to provide direction as needed. If full driveway access closure is required, advance notice will be provided and the project team will coordinate with the property manager to minimize disruptions. Please note that emergency access may impact these timelines.

Street parking

Street parking will be temporarily removed in active work zones to ensure the safety of motorists and construction crews. Access to street parking will be restored as work is completed in each section.

Stay connected

Sign up for our email updates to receive the most up-to-date information about this project.

Questions?

Have questions or want to learn more about the project? Contact the project team at

Project design

The project was guided by the Calgary Transportation Plan, the Beltline Area Redevelopment Plan, and Calgary’s Pathway and Bikeway Network (5A) Program.

Thank you to all residents and businesses for your valuable feedback during the engagement phases of this project. Your input, along with technical recommendations, has been incorporated into the final project design.

Plan views of 14 Avenue S. and 15 Avenue S., between 12 Street S.W. and Macleod Trail S.E.:

Project benefits

  • Enhanced Safety: The project will create a safer environment for pedestrians and wheeled users by implementing protected bike lanes, curb extensions, raised crosswalks, and improved lighting.
  • Improved Accessibility: The project will provide seamless connections for cyclists and other wheeled users, including a continuous two-way wheeling network. Additional wheelchair ramps will also make it easier for everyone to navigate the area.
  • Increased Mobility: Repaving 14 and 15 Avenue S and converting 14 Avenue S back to a two-way road will improve traffic flow and provide more efficient routes for drivers.
  • Health and Well-Being: By promoting active transportation options, the project will contribute to the health and well-being of Calgarians and visitors.
  • Reliable Water Supply: Replacing the water main on 15 Avenue S from 6 Street S.W. to 8 Street S.W. will prevent unexpected disruptions and ensure a reliable water supply for the community.

Frequently asked questions

Project background

Why was this project initiated?

During the 17 Avenue S.W. Construction Project, 14 and 15 Avenue were changed to one-way streets between 1 Street S.E. and 12 Street S.W., and temporary bike lanes were created. This project was initiated to address these temporary changes and support future growth and development in the Beltline area.

How does this project align with Council Priorities?

This project supports Calgary's council priorities by:

  • Enhancing safety and accessibility: Dedicated wheeling lanes for bike, scooter and skateboard users improve safety by providing protected spaces.
  • Promoting social equity: Protected wheeling lanes offer cost-effective, healthy, and inclusive transportation options, enhancing citywide accessibility goals and equitable access to transportation.
  • Addressing climate goals: Encouraging wheeling and walking reduces greenhouse gas emissions, contributing to Calgary’s climate resilience efforts.
  • Strategic infrastructure investments: This initiative is part of a broader strategy to invest in Calgary's infrastructure, improving safety, reducing congestion, and fostering a healthier community.

How is the project being funded?

This project is being jointly funded by the Government of Canada using the Active Transportation Fund and The City of Calgary under Calgary’s Pathway and Bikeway Network (5A) program,the Downtown Strategy program and other maintenance and operation funding.

How much does the project cost?

The project has $12.4 million in funding secured for design and construction construction – $7.5 million from The City of Calgary and $4.9 million from the Government of Canada.

Why was construction delayed to 2025, despite budget approval in 2023?

With the concept design complete and funding secured, construction was initially planned to begin in spring 2024. However, the start date was postponed for a few reasons:

  • Project scope clarification: We shifted the planned protected two-way wheeling lane from 15 Avenue to extend from 11 Street S.W. to northbound Macleod Trail, improving connectivity with the future entertainment district and LRT.
  • Parking assessment: We explored opportunities to conserve parking where possible while integrating the protected wheeling facility.
  • Community communication: Additional time was needed to notify property owners about new loading zones and changes to waste and recycling pick-up. Throughout 2024, we met with the community to discuss the upcoming changes and operational requirements. This included a community information session on September 10. Watch the recorded virtual session
  • Enabling works: We needed adequate time to complete enabling works. 

Water main construction

Why is the water main being replaced?

The City of Calgary takes a proactive approach to protecting and replacing aging assets. As part of the water main replacement program, this project will include a water main replacement for the water main running along 15 Avenue S from 6 Street SW to 8 Street SW. The water main replacement work will include new pipes and the installation of several redundancy features which will make maintenance work more efficient while helping to better support the ongoing water needs in the Beltline community.

Public engagement

Was public engagement done on this project?

Yes – In 2020 and 2021, there was public engagement conducted to gather feedback on the challenges and benefits of the 14 and 15 Avenue S corridors. The summary and results of the public engagement feedback can be found at: 14 & 15 Avenue S.W. Mobility Improvements | Engage (calgary.ca)

How was public engagement used?

We incorporated community feedback from the 2020 and 2021 engagement sessions, along with technical recommendations, into the final design for 14 and 15 Avenue S. Mobility Improvements project. 

Safety, accessibility and mobility

How does the project improve safety for Calgarians?

  • Protected Two-Way Wheeling Lane: Replacing the single lane painted wheeling lane on 14 Avenue with a protected two-way wheeling lane on 15 Avenue aims to reduce accidents between cyclists and vehicles.
  • Curb Extensions: Adding curb extensions to the sidewalks on 14 Avenue will shorten the distance pedestrians need to cross and improve sight lines for both pedestrians and drivers.
  • Raised Crosswalk: Raising the crosswalk at 6 Street S.W. and 14 Avenue S.W. will increase visibility and safety for pedestrians.
  • Improved Lighting: Rebalancing lighting levels along 14 and 15 Avenues will reduce dark spots, enhancing safety for everyone in the area.

How does the project improve accessibility for Calgarians?

  • Continuous Two-Way Wheeling Network: The new two-way wheeling lane will provide a seamless route for cyclists and other wheeled users to travel from the Victoria Park/Stampede LRT Station to the existing protected wheeling lane on 11 Street. Additionally, 15 Avenue is the best option for scooters to access businesses on 17 Avenue, as they are ‘geofenced’ to stop them from being ridden on 17 Avenue S.W. between Fourth and Eighth Street S.W.
  • Wheelchair Ramps: Adding wheelchair ramps will make it easier for pedestrians and individuals with mobility challenges to navigate the area.

How does the project improve mobility in the Beltline?

  • Repaving 14 and 15 Avenue S: Repaving these corridors will improve the road surface provide smoother traffic flow.
  • Converting 14 Avenue S Back to a Two-Way Road: This traffic flow change will offer more efficient and direct routes for drivers.

How will emergency services access my building if there is a protected bike lane in front of the building?

Emergency response teams are trained to ensure access to all properties during emergencies. In critical situations, all emergency vehicles—ambulances, fire trucks, and police cars—will be able to cross over the bike lane buffer without delay, ensuring that response times are not compromised. The bike lane buffer is engineered to allow for the safe passage of emergency vehicles.

What measures are being taken to address accessibility needs, especially for senior citizens during construction?

Our contractors are committed to using ramps and other methods to maintain accessible, flat, and firm surface for pedestrian detours.

Wheeling lane

Who can use the new wheeling lane?

The new wheeling lane is designed for: bicycles, e-bikes, skateboards, inline skates and shared e-scooters. These users can enjoy a fun, healthy, and eco-friendly way to get around. For more information on what modes of transportation are allowed where, please refer to this guide.

Parking and loading zones

What are the changes to parking and loading zones?

Parking on the north side of 15 Avenue between 12 Street S.W. and Macleod Trail is being removed to accommodate the protected wheeling lane. There are also changes to loading zones. Please see the map below for details:

Is The City of Calgary allowed to move/remove loading zones?

Yes, The City of Calgary can change loading zones under the Municipal Government Act (MGA) and its Traffic Bylaw. These laws allow municipalities to regulate traffic and manage roadways, including loading zones and curbside space.

Were parking studies used in making this decision?

Yes, two parking studies were conducted, analyzed, and included in the development of concept options shared during engagement. 

How do I move in / out of my building with the relocation of my loading zone?

We strategically relocated loading zones to minimize the impacts to residents and businesses along 15 Ave S. Please reach out to our project team at 1415ave@calgary.ca if you have specific questions.

What measures are being taken to address concerns about the removal of loading zones that are critical for the accessibility needs of senior citizens?

We are committed to minimizing the impact of loading zone changes on senior citizens by relocating affected zones nearby. Additionally, Calgary Transit Access (CTA) provides door-to-door service to ensure that seniors can be picked up easily. 

Are you changing parking permit zones? Are you changing the length of stay in parking zones?

At this time, we do not anticipate changes to parking permit zones. The Calgary Parking Authority will monitor these zones during and after the project completion and will make improvements and adjustments as needed.

Operational changes

How does this change the obligations for maintenance (boulevard lawn mowing and sidewalk snow clearing) in the area?

There are no changes to the obligations for grass mowing and snow clearing adjacent to private properties. The City of Calgary will clear snow in the wheeling facility. 

Why is the snow cleared on bike lanes better than the sidewalk?

Property owners are responsible for clearing sidewalks adjacent to their properties, as outlined in Section 67 of the Street Bylaw. The City manages snow clearing for sidewalks bordering City parks and other City-owned properties within 24 hours of the end of a snowfall. Sidewalks next to private property must be cleared by the property owner or occupant.

If a pathway or sidewalk on an existing clearing route remains uncleared 24 hours after snowfall, or if you believe it needs to be reviewed for clearing, please call 311 or submit an online request.

Will these changes impact how I access my waste and recycling removal?

Most of the corridor will not be affected by this design because residents have access to a back alley. For areas where residents and businesses do not have a back alley and the new design will impact their waste & recycling operations, the project team will contact property owners to discuss the details. If there are no impacts, we will not reach out.


This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​

undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null,undefined/null