Just east of Douglas Glen station, the Green Line will be elevated as it crosses 114 Avenue and Barlow Trail S.E. This package of work is to prepare the area for construction of the elevated guideway.
Scope of work
The scope of work includes drilling 22 concrete piles, including six abutment piles and 16 pier piles, utility relocations, and road realignment work, including widening medians for the piers that will be constructed to support the elevated guideway.
Location
| Milestone | Status |
|---|---|
| Demo existing road infrastructure (i.e., medians, curbs, etc.) | Completed |
| Piling | Completed |
| Utility work | In progress |
| New road reconfigurations and infrastructure | In progress |
| New asphalt |
April 2026 Update
Drilling of all 22 piles was completed in December, followed by the installation of temporary protection before work paused for much of January through March. Construction resumed in April with additional utility work and road reconfigurations. This phase will continue through June, culminating in the final top lift of asphalt across the entire project area.