78 Ave LRT Bridge

The 78 Avenue LRT bridge will run parallel to the Canadian Pacific Kansas City railway line. Expanding on the 78 Avenue Project completed in 2025, the bridge will carry Green Line trains over 78 Avenue S.E., which connects to Ogden Dale Road S.E. through the new roundabout built on the east side of the railway line.

Scope of work

Work includes preparing the site, implementing erosion and sediment control measures, building the bridge foundations and abutments, and constructing the bridge structure, which includes pre-cast concrete girders and a concrete bridge deck.

Location

78 Avenue S.E. and 27 Street S.E.

Start Date: 
October 2025
Anticipated Completion Date: 
October 2026
Construction Partner:

Milestone Status
Site preparation and road infrastructure demolition  Completed
Pile installation and foundation work  Completed
Bridge abutment construction  In progress
Concrete girder installation
Bridge deck construction

July 2026 Update

Construction of the 78 Avenue LRT bridge continued to make progress throughout July, bringing the project closer to the next major phase of work.

Crews are nearing completion of the bridge's retaining wall structures at both ends of the future bridge. Once this work is finished, crews will move on to preparing and reinforcing the bridge abutments, which support the bridge and connect it to the surrounding roadway.

Looking ahead, one of the project's most significant milestones is scheduled for next month when the bridge girders will be installed. These large concrete beams will form the main structure of the bridge span over 78 Avenue S.E.

Video

Video

Construction Progress

Images

An excavator preps the ground for pile drilling for the south bridge abutment in June 2026.
An excavator preps the ground for pile drilling for the south bridge abutment in June 2026.
Various heavy equipment on site in June 2026 beginning the piling work to build the foundation for the north bridge abutment.
Various heavy equipment on site in June 2026 beginning the piling work to build the foundation for the north bridge abutment.
Looking north at the project site in June 2026.
Looking north at the project site in June 2026.
Piling work happening for the north abutment, with preparatory work underway for the south abutment in June 2026.
Piling work happening for the north abutment, with preparatory work underway for the south abutment in June 2026.
Looking north in May 2026 where one of the future bridge abutments will be constructed.
Looking north in May 2026 where one of the future bridge abutments will be constructed.
Looking north at the project site in May 2026.
Looking north at the project site in May 2026.
Looking north at 78 Avenue S.E. and the Canadian Pacific Kansas City (CPKC) railway line. The 78 Avenue LRT Bridge will cross 78 Avenue on the west side of the CPKC railway line.
Looking north at 78 Avenue S.E. and the Canadian Pacific Kansas City (CPKC) railway line. The 78 Avenue LRT Bridge will cross 78 Avenue on the west side of the CPKC railway line.
The bridge will be built beside the recently completed underpass that connects 78 Avenue S.E. and Ogden Dale Road S.E., allowing for better and safer access into the industrial area.
The bridge will be built beside the recently completed underpass that connects 78 Avenue S.E. and Ogden Dale Road S.E., allowing for better and safer access into the industrial area.
 Looking east at the project site in October 2025.
Looking east at the project site in October 2025.
Looking north at the project site in October 2025.
Looking north at the project site in October 2025.
Looking north from behind the new roundabout in October 2025.
Looking north from behind the new roundabout in October 2025.