MSF Site Grading, Building Foundations and Utilities

The Maintenance and Storage Facility (MSF) will serve as the operational backbone of the Green Line LRT. This contract includes the site preparation, underground infrastructure, and foundation work needed to support future facility construction and long-term operations.

Scope of work

Work includes reshaping and grading the land, building retaining walls, creating five drainage ponds, and developing the Park and Ride area and other paved public spaces.

Crews will also install underground infrastructure, including utilities, power and communications systems, drainage networks, and stormwater infrastructure, while relocating or protecting existing services as needed.

Foundation work for the facility will include concrete structures and the underground systems needed to support the building, creating the base for future construction.

Location

North of 126 Ave S.E., west of 52 St S.E., east of 40 St S.E.

Start Date: 
May 2025
Anticipated Completion Date: 
December 2026
Construction Partner:

Milestone Status
Topsoil stripping and site grading  In progress
Foundation construction  In progress
Retaining wall construction  In Progress
Underground utility installation  In progress
Communications and underground infrastructure installation  In progress
Stormwater pond construction  In progress

August 2026 Update

Construction continues to advance at the future MSF site. Following mobilization in June, crews began removing topsoil and carrying out rough grading work to prepare the site for major construction activities.

Foundation work remains underway, with concrete footing pours continuing across several areas of the facility. As part of this work, anchor bolts supplied through a separate steel contract have begun to be installed in the concrete foundations, helping prepare the site for structural steel installation planned for next year.

Construction of retaining walls is also progressing, with mechanically stabilized earth (MSE) wall excavation ongoing. Work will continue through the fall as foundation construction, retaining wall development, and underground infrastructure activities advance across the site.

Video

Video

Construction Progress

Images

An aerial view of the site looking northwest in early July 2026.
An aerial view of the site looking northwest in early July 2026.
Stripping topsoil and grading the site in early July 2026.
Stripping topsoil and grading the site in early July 2026.
Foundation work underway in early July 2026.
Foundation work underway in early July 2026.
Newly completed concrete foundations and ongoing formwork installation for the next phase of foundation construction in late July 2026.
Newly completed concrete foundations and ongoing formwork installation for the next phase of foundation construction in late July 2026.
An aerial view of the site looking northwest in late July 2026.
An aerial view of the site looking northwest in late July 2026.
Formwork installation underway in preparation for a concrete wall pour in late July 2026.
Formwork installation underway in preparation for a concrete wall pour in late July 2026.