MSF Structural Steel

The Structural Steel contract supports delivery of the Maintenance and Storage Facility (MSF) by providing the primary structural framework that will enable the facility to house, maintain and operate the light rail vehicle fleet.

Scope of work

The scope of work includes the engineering, detailing, fabrication and installation of primary structural steel components for the MSF and includes in‑shop application of protective coatings, comprehensive quality control procedures and adherence to all applicable codes and industry standards to ensure constructability, durability and long-term operational performance.

Execution of the work will be closely coordinated with the other contractors that will oversee construction of the facility, with an emphasis on integrated planning and value engineering. This collaborative approach is intended to optimize material use, sequencing and installation efficiency while supporting schedule and cost certainty.

Location

North of 126 Ave SE, west of 52 St SE, east of 40 St SE

Start date:
May 2026
Anticipated completion date:
August 2027
Construction partner:

Milestone Status
Material procurement Completed
Fabrication In progress
Deliveries to site
Installation

October 2026 update

Progress continues on the structural steel package for the future MSF, with fabrication activities now underway.

The first deliveries of structural steel to the MSF site are expected to begin in November and will continue throughout the winter and into the spring.

Installation of the structural steel is expected to begin in the spring, marking another major step in the construction of the facility.

Images

Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
Fabrication work underway at Supreme Steel’s factory near Edmonton in November 2026.
A Supreme Steel employee showing the virtual model of the MSF in November 2026. This model plays an important role in the fabrication process, ensuring everything is made correctly and will fit together once on site.
A Supreme Steel employee showing the virtual model of the MSF in November 2026. This model plays an important role in the fabrication process, ensuring everything is made correctly and will fit together once on site.
Stockpiles of steel outside Supreme Steel’s fabrication shop in November 2026. Raw steel gets delivered here first, before being brought inside to begin the fabrication process.
Stockpiles of steel outside Supreme Steel’s fabrication shop in November 2026. Raw steel gets delivered here first, before being brought inside to begin the fabrication process.
An aerial view of Supreme Steel’s fabrication shop, outdoor storage and head office in November 2026.
An aerial view of Supreme Steel’s fabrication shop, outdoor storage and head office in November 2026.