Caution Updated:

  • New! The Bow River is exceeding safe flow rates for boating and swimming. The Calgary Fire Department has issued a boating advisory. For your safety, stay off the river. Learn more

Search Close

Ogden Road Realignment

The realignment of Ogden Road S.E. between roughly the Canadian National Railway rail bridge and 69 Avenue S.E. is required to make room for the Green Line alignment, which will run between the realigned Ogden Road and the Canadian Pacific Kansas City railway line.

Throughout construction, parking and access to Pop Davies Athletic Park will be maintained, along with vehicle, pedestrian, and cyclist access along Ogden Road and Millican Road. The informal gravel parking along the west side of the current Ogden Road will be permanently removed as part of this work to make room for the new Ogden Road.

Scope of work

In addition to the road realignment, the scope of work includes installing a water mainline, storm and sewer lines, adding a multi-use pathway along the west side of Ogden Road, constructing a new asphalt parking lot with approximately 100 stalls at the south end of Pop Davies Athletic Park, and completing landscaping and other related work.

Location

Ogden Road S.E. and Millican Road S.E.

Start Date:
September 2025
Anticipated Completion Date:
August 2026
Construction Partner: 

Milestone Status
Strip topsoil  Completed
Install watermain  In progress
Install storm trunk line  In progress
Build new parking lot at Pop Davies Athletic Park In Progress
Demolish existing Ogden Road
Build new Ogden Road

May 2026 Update

Work continues on the Ogden Road realignment project, with several key activities advancing across the site. Excavation for the stormwater tank in the new parking lot at the south end of Pop Davies Athletic Park is now complete.

Work on the storm trunk line is progressing, with backfilling currently underway. Storm trunk lines play an important role in managing runoff by collecting water from smaller sewer lines and directing it safely to a major outfall.

The project team is also reviewing options for the remaining watermain tie-in at the north end of the project site, which will connect the new infrastructure into the existing system. 

The contractor has also adjusted their site setup at Pop Davies Athletic Park to accommodate the recreation season, including providing a revised parking arrangement to help maintain access for sports users while construction continues nearby.

Video

Images

Aerial view of the project site north of Millican Road S.E., with watermain installation work underway in April 2026.
Aerial view of the project site north of Millican Road S.E., with watermain installation work underway in April 2026.
An articulated dump truck moves dirt across the project site in April 2026.
An articulated dump truck moves dirt across the project site in April 2026.
Aerial view of the project site, looking south along Ogden Road S.E. in April 2026.
Aerial view of the project site, looking south along Ogden Road S.E. in April 2026.
An excavator backfills dirt over a portion of the recently installed watermain in February 2026.
An excavator backfills dirt over a portion of the recently installed watermain in February 2026.
An excavator and bulldozer backfilling a portion of the watermain installation near Millican Road S.E. in February 2026.
An excavator and bulldozer backfilling a portion of the watermain installation near Millican Road S.E. in February 2026.
A compactor rolls over the dirt to ensure proper compaction above a portion of the recently installed watermain in February 2026.
A compactor rolls over the dirt to ensure proper compaction above a portion of the recently installed watermain in February 2026.
The removal of grass and topsoil is to prepare for a new water mainline that will be installed parallel to the existing Ogden Road. The new Ogden Road will eventually run over top of this new water mainline.
The removal of grass and topsoil is to prepare for a new water mainline that will be installed parallel to the existing Ogden Road. The new Ogden Road will eventually run over top of this new water mainline.
Ogden Road S.E. looking northwest in September 2025 before work began
Ogden Road S.E. looking northwest in September 2025 before work began