Maintenance and storage facility grading and site servicing

Contract Status
- A request for proposals was posted on April 17, 2025.
- Submission deadline was May 7, 2025.
- Contract was awarded to KLS Earthworks & Environmental.
(Image: Maintenance and storage facility site)
As part of the Green Line, The City will construct a maintenance and storage facility (MSF) north of 126 Avenue S.E., between 40 Street S.E. and 52 Street S.E.
The MSF is a large garage where light rail vehicles are cleaned, maintained and serviced. This summer we’ll begin preparing the site for construction, so the MSF is ready to house Green Line’s fleet of light rail vehicles once they start arriving.
Scope of Work
This work addresses the initial grading and site servicing works for the MSF.