Feeder Main area construction
Helping our community navigate construction
To protect Calgary’s drinking water system and ensure it continues to serve the city reliably into the future, we are reinforcing and replacing the Bearspaw South Feeder Main (BSFM).
We know that construction has been disruptive and will continue to impact daily life for residents and businesses in the area. This page is here to support you by bringing together clear, up‑to‑date information about construction and related activities from Bearspaw South Feeder Main. Our goal is to help you easily find the information you need, stay informed about what’s happening nearby, and remain connected to your community throughout the project.
Residents of 34 Avenue N.W.
Where is construction happening?
Bowness
Bowness
| Location | Closure details | Anticipated schedule | More information |
|---|---|---|---|
| Location : Shouldice Athletic Park |
Closure details:
|
Anticipated schedule : January - TBD |
More information :
|
| Location : 79 Street N.W. to 80 Street N.W. on 34 Avenue N.W. |
Closure details:
|
Anticipated schedule : Beginning June 4 for approx. 10 weeks. |
More information :
|
| Location : 85 Street N.W. to 86 Street N.W. on 34 Avenue N.W. |
Closure details:
|
Anticipated schedule : Beginning June 4 for approx. 10 weeks. |
More information :
|
| Location : 34 Avenue N.W. between 73 Street N.W. and 89 Street N.W. |
Closure details:
|
Anticipated schedule : Beginning June 1 for approx. 8 weeks. |
More information :
|
| Location : 69 Street N.W. & 29 Avenue N.W. |
Closure details:
|
Anticipated schedule : Beginning May 25 - August |
More information :
|
| Location : Eastbound lane on 16 Avenue N.W. at Home Road. |
Closure details:
|
Anticipated schedule : Beginning June 8 - September |
More information :
|
| Location : 73 Street N.W., between Bonita Crescent and 34 Avenue N.W |
Closure details:
|
Anticipated schedule : Construction start date will be rescheduled. |
More information :
|
| Location : 34 Avenue N.W., from 86 Street to 87 Street N.W. |
Closure details:
|
Anticipated schedule : Beginning July 4, 2026, for approx. 10 weeks. |
More information :
|
| Location : Green space at 89 Street N.W. between 33 Avenue N.W. and 34 Avenue N.W. |
Closure details:
|
Anticipated schedule : Beginning June 24, 2026 to December 2026. |
More information :
|
| Location : 34 Avenue N.W., between 73 Street N.W. and Bowcliffe Crescent N.W. |
Closure details:
|
Anticipated schedule : Beginning August 4 2026, for approx. 10 weeks. |
More information :
|
Montgomery
Montgomery
| Location | Closure details | Anticipated schedule | More information |
|---|---|---|---|
| Location : East of Monserrat Drive and North of 16 Avenue N.W. |
Closure details :
|
Anticipated schedule : January 23 – December 2026 |
More information:
|
| Location : Montgomery Blvd. N.W. |
Closure details :
|
Anticipated schedule :
January 2026 – TBD |
More information:
|
| Location : 16 Avenue N.W. between Monterey Avenue N.W. and Montgomery Avenue N.W. |
Closure details :
|
Anticipated schedule :
May 13 for approx. 2 months |
More information:
|
Parkdale
Parkdale
| Location | Closure details | Anticipated schedule | More information |
|---|---|---|---|
| Location : Edworthy Park Parking Lot |
Closure details :
|
Anticipated schedule :
January 23 – December 2026 |
More information :
|
| Location : Point Mckay Park |
Closure details :
|
Anticipated schedule :
January 23 – December 2026 |
More information :
|
| Location : Douglas Fir Trail & South Parking lot. |
Closure details :
|
Anticipated schedule : November 2025 – December 2026 |
More information :
|
| Location : Edworthy Park Bathrooms |
Closure details :
|
Anticipated schedule : October 2025 – October 2026 |
More information :
|
Construction updates
Construction notices
- June 29 construction notice
- June 24 construction notice
- June 22 construction notice
- May 21, 2026 construction notice
- April 29, 2026 construction notice
- April 9, 2026 tie-in construction notice
- March 18, 2026 construction notice - 16 avenue N.W.
- March 18, 2026 construction notice - 33 avenue N.W.
- March 11, 2026 construction notice
- March 2026 construction notice
- February 2026 construction notice
- January 2026 construction notice
- January 2026 geotechnical notice
Bearspaw South Feeder Main Newsletter
BSFM Community Resource Centre
Chat directly with city staff about the project and get support during construction. The Community Resource Centre will serve residents of Bowness, Montgomery and Parkdale affected by the Bearspaw South Feeder Main repairs.
Location: Bowness Community Association: 7904 43 Ave N.W.
Hours:
- Monday and Wednesday, 9 a.m. – 5 p.m.
- Tuesday and Thursday, 10 a.m. – 7 p.m.
Construction Liaisons
Two Construction Liaisons are assigned to this project to support people impacted by construction. They are also on-site at the CRC (Bowness Community Association) on Wednesdays, 10 a.m.-12 p.m.
Eric Wu
Email: eric.wu@calgary.ca
Phone: 403-371-3656
Chris McGeachy
Email: christopher.mcgeachy@calgary.ca
Phone: 403-826-0100
Available supports:
- Residents can connect to social and emotional support services.
- Listen to residents’ concerns and experiences, answer questions about the project, and help connect people with available resources, while ensuring community feedback is shared with the project team and partners to inform future plans.
- Give information about upcoming outreach, community engagement and special events.
Information session videos
For those who are unable to join us at our community information sessions, we encourage you to watch our videos to learn more. These presentations provide a brief background on the Bearspaw South Feeder Main, upcoming work and what to expect, and available community resources.
Community Information Session presentation - February 24, 2026
Community Information Session presentation - March 30, 2026
Pre-construction information Session - April 21, 2026
Community mitigation
Until the replacement pipe is in service, we cannot guarantee the feeder main will not break again. Public safety remains the top priority and we are ensuring there is a community protection plan in place. There are several mitigation measures are in place to help protect communities in the event of a feeder main failure. These include flood barrier adjustments along the Bow River, temporary pathway barriers with a ramp to maintain access, a staging area at Shouldice Athletic Park for pumps and equipment, and ongoing maintenance of catch basins.
The City continues to evaluate additional mitigation options and your safety and access to water are our top priorities. We will keep you updated and provide clear instructions if the situation changes.
Measures in place to protect our community
The community protection plan is meant to ensure that we are protecting the community in the best way possible should we have a break.
Examples of mitigation measures in place in case of a feeder main break
- Crews have cleared catch basins, opened river outflows, and replaced select manhole covers with ones that will allow water to drain more rapidly in the event of a pipe break.
- Two segments of the Bow River flood barrier along Montgomery Blvd. N.W. were removed so water can flow directly into the river.
- Temporary barriers have been installed along the Bow River pathway next to Parkdale Blvd. N.W.
- A pathway ramp is being built over the barrier at Parkdale Blvd and 32nd Street N.W. to restore access to the Bow River Pathway.
- A staging area is being set up in Shouldice Athletic Park to house pumps and equipment which can be quickly deployed if there is a release.
- During the Return to Service you will see City of Calgary crews and emergency responders in the area to ensure a rapid response in the event of a pipe break.
- We continue to monitor the feeder main for anomalies and wire breaks that may provide us with an early indication of any problems.
Community mitigation checklist
As a precaution, we are asking that all community members continue to prepare. We’ve provided a checklist to support your precautionary preparation.
Traffic impacts
As part of the Bearspaw South Feeder Main construction, traffic impacts will be in effect in the community. We appreciate your patience while this work is underway. For the most up‑to‑date information, please visit the City’s traffic map. Detour maps are included below.
Bearspaw South Feeder Main resources
-
Learn more about the new replacement pipe project
-
Learn more about urgent pipe reinforcements completed in March/April 2026
-
Learn more about the 3rd party review
Contact us
If you have questions or feedback about Bearspaw South Feeder Main, we’d like to hear from you.